Major overhaul of heating main TM-5 in Astana
Location::
Saryarka district, Astana, Akmola Region.
Project name:
Major overhaul of heating main TM-5 along pipeline T-1 from the turning point near 70 Respubliki Ave. to chamber UT-4 near 62 Respubliki Ave., with DN700 sectional shut-off valves tied into T-1 and T-2 at chamber UT-8 near 46 Respubliki Ave.
Expected funding sources and arrangements:
budget financing under programme 029, "Development of the water supply and sanitation system".
Construction period:
2025 (1 month)
Total estimated construction cost:
KZT 222,142.931 thousand, including construction and installation works — KZT 96,983.705 thousand, equipment and other items — KZT 125,159.226 thousand.
Description:
The project covers the repair of a section of the T-1 supply heating pipeline from the turning point near 70 Respubliki Ave. to chamber UT-4 near 62 Respubliki Ave., with DN700 sectional shut-off valves tied into T-1 and T-2 at chamber UT-8 near 46 Respubliki Ave. The pipeline is laid underground using pipes in PPU-PE insulation. The design provides for laying within the existing ducts and relieving slabs. The total length of the heating networks being repaired is 226.6 m.
  • Heat mechanical design (TS)
  • Reinforced concrete structures (KZh)
  • Heating networks. Operational remote monitoring system (TS.SODK)
  • coordination of the building services with each other
  • development of the construction organisation design (POS) and estimate documentation
Site location plan
Heating network plan
Pipeline installation drawing
Sections 1-1 and 2-2.
Structural section
Certificate of acceptance into operation, TM-3
Contacts
Address:
Astana, Saryarka district, Saryarka St., building 8/1, NP­19
Phone:
8 (778) 818-83-21
E-mail:
info@astanaliq.kz
Astanalyq Kazakhstan Engineering and Design Institute LLP
Made on
Tilda